Monday, August 24, 2009

Inspections and Getting Ready for the Last Pour

Today was our day of inspections. First, the City's building inspector came out for the electrical inspection. Pending a few items, we passed the inspection: one box had too many wires in it, one wasn't raised out of the floor high enough, and ... we have to have a light switch for exterior lights next to each exterior door including all 10 sliding glass doors - needless to say at this stage that's impossible, so we're going to have the lights either on a timer or a motion sensor. Ugh.

The next visit from the City was the erosion control inspector. He was just doing his usual "post storm" rounds, and commented that our erosion control measures looked good - in particular, the dug-out silt fence on the south side (see my earlier post). Phew!

And lastly, the City's urban forester stopped by to check on whether we had managed to mangle any trees. Since we hadn't all was well on that front, too.


Some more progress. First, a picture of the radiant heat pipes on the first floor that Mike and I had laid over the weekend, getting ready for the concrete pour on Wednesday.

Next, Tim Griffin from ARS came, with an ARS field service technician and his team of two installers. We had set them a hard task: the TRV (total recovery ventilator - a Lifebreath product that's a combination of both and ERV plus an HRV) that we had bought for them to install was new to them, and they had to spend some time getting familiar with it. After a bit of head scratching, and realizing it was easiest with the manual held upside down (really!) they had figured it out. Their installers cut the floor penetrations, both for the TRV, and for the ducting for a future "should-we-ever-need-it" Air Conditioning system. One word about their crew: they were the cleanest people to work on our project yet. The minute they saw our shop vac, they started using it. I was very pleased.

The floor penetrations they cut, and fitted with boots, are one of the last things we needed to get ready to pour concrete. The only things still left are a few pieces of blocking (so the concrete doesn't run into places where we don't want it, like the basement, or our windows), and we'll be ready!


(And, by way of explanation, in case you're wondering about ERVs and HRVs ... an HRV is a Heat Recovery Ventilator. It extracts the sensible heat - the heat you can feel - from the exhaust air and transfers it to the fresh supply air. An ERV, an Energy Recovery Ventilator, does that plus it also transfers the latent heat - the heat it took to evaporate moisture into the air - and so has some dehumidifying effect as well. The drawback of the pure ERV unit is that, since its core is made from paper, it is susceptible to damage from freezing in cold temperatures. Combining both an ERV and an HRV and adding a defrost cycle fixes the freezing problem, gives you the best of both ERV and HRV, and results in what Lifebreath calls a ... TRV - Total Recovery Ventilator.)

Responsibilities

The last few days have been a time to take care of some responsibilities.

Remember a post way at the beginning of this journey about me being the Responsible Land Disturber? Really what that means is that I'm the person to make sure muddy water doesn't run into our neighbours' yards or into the street. Well, we had quite a bit of rain over the weekend, and combined with the digging from the folks who put our gas line to the house (National Pipeline, under contract to Washington Gas), the silt fence on the south side of our lot was covered up to the top in mud. So, being responsibly, I spent a few hours on Sunday digging out the silt fence. Not very glamorous, but necessary.


The other responsibility we had was to make Mrs Brown's lot look nice again, after borrowing it for so long. I found some more leaf mulch at the City (free!) and hauled another (we had already previously done a few mulch runs) four truck loads to the lot. This is what her lot looks like now. Better?

Saturday, August 22, 2009

Long Progress Report




Before I head off to San Diego for a quick work trip (27 hours out of town, 12 of which will be at an airport/on an airliner), I wanted to give a brief progress report on construction.

While we remain frustrated that several subcontractors think it's perfectly OK to not show up when they say they'll be there, there are some bright spots:

Tim Griffin from ARS has been working with us to calculate the HVAC loads for the house and determine the ducting requirements. An energy efficient, air sealed house is a lot different to work with than conventional construction. And our passive solar design adds another twist. Tim has experience with green construction and the Earthcraft Virginia program. And our budget constraints offered another challenge. Tim designed a system and lined up a crew - they're scheduled to start the duct installation on Monday.

The last four days were absolutely exhausting. Andreas had three off-days in a row, so I took some vacation days from work and also spent Wednesday morning on the project. We worked our tails off on the house. I wish everyone we're paying to assist and manage this construction project were doing the same.

Wednesday morning, Aaron and I installed the fan and the fresh air intake system to the fireplace and set that in place.

Starting on Thursday, I spent a full 10 hours on my hands and knees vacuuming the first floor of the house with the shop vac so there would be no dust and debris to contaminate the concrete floor when it's poured next week. Despite multiple requests for workers to clean their shoes before entering, most folks just kept walking in, tracking more dirt for me to vacuum up. I don't mean to sound so negative. But, really, how difficult is it to clean off your shoes before walking into the house, especially after you've been specifically asked to, with the reason for the request explained to you?

While I was inside vacuuming, Andreas was completing numerous projects, including digging a trench to install the drain tile so the sump pump outflow will run under our intended garden area into the stream at the back of the lot. It looks great and is ready for Bernie to install the two cast iron sump pumps next week.

Elmer sent a crew on Thursday evening to install the nailer strips along the exterior walls (the TerraBrick walls). This was to fix mistakes Aaron had made when he cut and installed nailer strips some time ago, but they were of varying heights, so they all had to be removed and trashed. One of the considerations when building with a solid exterior is how to place electrical outlets along those walls. Ours will be centered in a baseboard. The size of the nailer strip in our house is extremely important, as the electrical boxes are screwed into that, and it also is the nailer strip for the baseboards. It needed to be a specific height so that the 1.5" of concrete would not come into the electrical boxes and so the electrical outlets would be a consistent height throughout the baseboards. It was good to get that corrected, since we're hoping that Bartley will be able to come on Wednesday to pour the concrete floor on the main level of the house.

After months and months attempting to get Washington Gas to install service at our house, their subcontractors came on Thursday early afternoon to do the street cut. First thing Friday they were back to trench on the lot and bring the gas line to the back of the house. It was only after I made a phone call to an executive at Washington Gas & Light Holdings that we saw any action. That's all water under the bridge now, but here's a special thanks to WGL Holdings' Marcellous Frye for getting the right people on the job for us.

Piedmont Roofing's crew was supposed to come on Thursday, but they ran over on another project, so they were to be on our project early Friday morning. Mid-afternoon Friday, they finally showed up. But they were not prepared to do what Aaron said he asked them to do. So they installed the roof boots on the plumbing and radon vent and promised to come back on Saturday. They didn't show up this morning. They had several hours of work time before the rain, so it's disappointing they were no-shows.

Tom (the electrician) came on Friday morning and finished everything he needed to for the electrical rough-in inspection. Andreas scheduled that for 9am on Monday.

Accurate Insulation was scheduled to come Friday morning to install the rain gutters. Only one person showed up. He looked at our house and said he couldn't do it himself, so he'd have to get help and come back on Saturday. He said he'd be at our lot by 8am. We showed up at 8:10 and he was there, with a co-worker, only to inform us that the job was COD. Aaron never sent us a contract and most vendors accept payment afterwards. So I drove home to get the checkbook and was back on-site an hour later only to learn that the crew didn't have screws long enough to attach the downspouts through the EIFS and into the concrete columns. So I drove to Brown's Hardware in Falls Church, but they didn't have any 5" stainless steel screws the Accurate folks requested. I then went to Home Depot. They didn't have any either, so I bought some 4" screws (the longest they had) and some 5" lag bolts. As it turned out, neither of those options worked, but the 4" TapCons I had in my truck (leftover from affixing the extruded foam board to the basement walls) fit the bill. All of that running around was a waste of time. After they left, Andreas and I attached some drain tile to direct the water away from the house. As soon as we were done, the rain started to fall. So I don't have any pictures of the gutter and downspouts yet.

After weeks and weeks and weeks, Quality Window and Door sent a service guy out to repair the sliding glass doors that were difficult to slide, install some weather stripping on a sliding glass door that didn't have some, and fix the loose-fitting locks on two of the swinging exterior doors. This was the third service guy to come out to work on the doors. Well, he got most of it done, but we'll need a fourth visit. He didn't have any weather stripping with him, so he couldn't do that. He fixed the two sliding glass doors. And he fixed one of the two locks. Maybe the fourth time will be the charm and someone can bring weather stripping and properly fix that remaining jiggly lock problem. How difficult is this...really?

Loudoun Stairs supposedly was going to come by on Friday to measure for the staircase to the basement and also bring some photos of what the staircase would look like. But they didn't show up. Can anyone recommend a good (but affordable) stair company for some basic stairs into the basement?

Andreas and I installed the pex tubing on the first floor this afternoon (Saturday). We didn't finish until after dark so, again, no photos. Clearly we were focused on getting the job done and not on documenting that for the blog. Sorry folks. We'll snaps some pics later.

While I'm on a flight to the West Coast tomorrow, Andreas plans to clean the basement floor so that can dry and allow us to test some sample coloring for the concrete floor stain when I'm back on the project Tuesday evening. There's a lot more on the schedule for next week, but I guess it will get done only if the subcontractors show up. These days, I'm not holding my breath for that! And please don't ask me about the clerestory windows.



Monday, August 17, 2009

Short Update

I'd love to write a nice, long update describing in detail everything that's been going on. But I can't. That's because very little has happened at the house. It's extremely frustrating that more is not happening. But people aren't following through on their commitments and there's little control we have over subcontractors. On the positive side, the plumbing passed the rough-in inspection, so we have a green light with that. Elmer's crew finished the cement parging, but they left a huge mess we're still trying to get cleaned up. Aaron brought his pressure washer, so we'll be cleaning the basement floor thoroughly and then staining it. And don't even ask about the windows. You do not want to get me started on what an awful, painful, unbelievable situation this has been.

I know it will be wonderful when it's all done. But with most folks slow to respond or not showing up when they promise, I doubt this house ever will be done.

Thursday, August 6, 2009

Parging's Complete, Plumbing Rough-ins Complete


I'm a day late in posting this - I had trouble with my Internet connection last night after I uploaded the post on the mulch. Elmer's crew completed the cement parging of the interior walls yesterday.


The crew helped our construction manager, Aaron, place the fireplace in its spot in the living room. Unfortunately, when they uncrated the fireplace, they noticed that some of the stones that run along the base of the fireplace were cracked and others were chipped. I guess that's understandable, considering the fireplace was shipped all the way from Belgium. (Don't talk to me about that carbon footprint - actually, it's an exceptionally efficient fireplace that can heat our entire first floor with just a few logs.)




Our plumber, Bernie with Clarke County Plumbing, installed the rough-ins for the basement bathroom and ran the lines for the sump pumps.











Wednesday, August 5, 2009

Stabilizing Soil



On Saturday, we spent much of the day working to stabilize the soil by placing mulch on our lot and the back yard of the house next door (which we borrowed for a period of time during construction). We used up all of the leaf mulch the City of Falls Church had, and we used a good bit of their wood chip mulch as well. We'll find some more leaf mulch, either in Arlington or Fairfax County, so we can finish placing that in the neighbor's yard and then seed a lawn to replace the lawn/weed mixture we killed with the clay earth stored there for several months.

Friday, July 31, 2009

Parge Away!






Elmer's crew spent some time today making a huge mess of the house. But that was expected. Parging the walls with cement is not the cleanest task during home construction. I came to the house tonight to install the RG6 cable wire into each room, and snapped some photos with my iPhone of the parging. I suspect they only worked 1/2 day, given that only a small area was done and we had some thunderstorms this afternoon. Check out their progress so far.

Thursday, July 30, 2009

100th Blog Post






This marks our 100th post. And I'm happy to report there's been some more progress. In the past couple of days, our recycling dumpster was hauled away. We filled two dumpsters during the construction, which is less than 1/2 what typical construction sends to the landfill. And many of the items placed in our dumpster will be recycled instead of dumped.

Bob Demarr's crew spent about 7 hours fixing the problems with the rough grading caused by Bartley Corp's team. Bartley's job foreman admitted to Andreas that they really don't do grading work - they don't have the right equipment or labor. That showed with the mess they created. It took Andreas more than 30 hours to dig out tree protection fencing Bartley ran over with a machine and dumped dirt on top of. I spent another 10 hours uncovering the Holly Tree roots they graded over, even though the root protection zone is clearly marked on the grading plan. Alas, we're now on the right path with grading. Demarr's crew hauled away a few truck loads of dirt today, leaving the lot looking much better than it has the past six months!

Inside, Bernie from Clarke County Plumbing, continued work on the rough-in plumbing. He put the vent pipes through the roof (now Piedmont Roofing will come back to seal that all up) and worked on the basement bathroom. Ferguson delivered the tub, toilet wall carrier and shower faucet rough-in and Bernie will install that soon. He also drilled through the EIFS to prepare for the outdoor shower piping, the hose bibs, and the sump pump piping. Unfortunately, he drilled the sump pump holes too high - the sump pump pipes were supposed to come out beneath the deck - so we'll have to work with Bernie to get that resolved.

Also inside, Aaron laid the pex tubing for the bathroom radiant floor heating. I want the shower floor to be as toasty warm as the rest of the bathroom floor, so that had to be laid today so a first layer of concrete can go over the pex tubing in the shower tomorrow. Bernie can then protect the shower floor properly with the rubber membrane and when the concrete floor is poured, it will work out perfectly.

Elmer's crew started work today on the parging. They spent the day applying a metal lathe around the doors and windows. They'll finish that tomorrow then apply the thin layer of cement to the walls and round out the edges by the doors and windows. After that cures, I can apply the American Clay Earth Plaster over the cement parging.

Jay with Quality Window & Door hasn't provided the exact date yet for the corrected clerestory windows to be delivered - hopefully that will be in the early part of next week so the cedar siding can go on Thursday morning.

Sunday, July 26, 2009

Staining Cedar






There's a particular look we were going for with the cedar stain and I think we're achieving it! At Amicus Green Building Center in Kensington, MD, we purchased a "one coat only" stain that's made from plant oils. The color we chose is mahogany, which will give the beautiful orange-ish, red color we'd like for the cedar. This will be beautiful with the lighter color stucco below and the dark metal roof. As I mentioned in an earlier post, the cedar arrived on Friday. I had ordered the stain from Amicus a couple of weeks ago, it arrived, so I picked it up after work on Friday evening and I spent the weekend staining. I got most of the shiplap cedar siding done on three sides, and all of the cedar trim on one side. I only made it through a couple of the longer cedar fascia boards before running off to a friend's 60th birthday dinner. In any case, I made a lot of progress and Andreas is off tomorrow so he'll pick up where I left off - finishing the cedar fascia boards and the final side of the cedar shiplap siding. I have some more shiplap to stain for the outdoor shower, but there's not a big rush to get than completed since I'll build that fencing around the shower at my leisure. Here are some pics of the stain and the wood - both finished and unfinished.

Progress!






While I was out of town, a lot of things happened at the house. I need to get out of town more often, so progress continues!

Bob DeMarr and his team did the street cut and trenching to the house, as you saw in the photos from the other day. Later in the week they drilled through the 12" thick concrete foundation to bring the water and sewer lines through into the house. Meanwhile, Bernie from Clarke County Plumbing was on-site working on the rough-ins for all of the plumbing - bathrooms, kitchen, laundry, etc. Southland Insulators came back to finish the air sealing in the first floor. And Bartley's crew came back to re-do the deck piers they excavated and poured way back in February (the ones that collapsed when the excavation for the basement began). So we now have footers for the deck framing that will begin on Monday. Also this week, Bernie will continue with the rough-in plumbing to connect the sewer/water lines and the sump pumps; Elmer will be on-site to do the parging over the interior TerraBrick walls (except the pantry, which we're leaving as bricks to show them off), and Aaron will continue with his to-do list of items he needs to follow-through on, such as correcting the height of the baseboard outlets, installing the fireplace chimney and 6" duct for the range hood, etc. We're close to plumbing and electrical rough-in inspection time, which is very exciting.

The latest word on the corrected clerestory windows is they should be here early next week. Once that's done, we'd like to move quickly on finishing the exterior, laying the radiant floor pex tubing, and pouring the concrete first floor so we can then close-in the walls with drywall. It now looks like we're aiming for a mid-October move-in. Stay tuned!


Saturday, July 25, 2009

TW Perry Rocks

I am at the house to stain the beautiful cedar siding we ordered through TW Perry. Actually all of our wood products have been supplied by them. Our sales rep, Ricky Bise, has gone out of his way to provide exceptional customer service. The cedar is the latest example of that. I have only this weekend available to stain the cedar and it was running a day behind from the mill, so it wasn't going to arrive on our lot until Monday. Needless to say, that wouldn't work with my tight schedule. Ricky sent his assistant, Jose, to get the cedar and deliver it to our lot yesterday so I could stain it this weekend. Ricky lost an important team member for several hours during a busy day. But it made all the difference in the world for our project and we are incredibly grateful. If you're building or renovating, give Ricky a call in TW Perry's Gaithersburg, MD office at 301.840.9600. He is extremely competitive in pricing and pulls out all the stops to ensure his customers are happy. Many thanks, Ricky.

Thursday, July 23, 2009

The Big Dig

Just a few pictures of our own version of the big dig: the sewer pipe to our house, the City's water meter, and the patched street. Nice job from the guys at DeMarr!








Saturday, July 4, 2009

EIFS, Act 5

Andreas is out of town for work and I'm back from my trips, so it's my turn to blog again. I hope you have an enjoyable Independence Day holiday today.

The crew from Seasons Services finished up the EIFS installation on the Southern side of the house on Friday morning. They work quickly! They've taken down almost all of their scaffolding as well. And they've caulked around all of the doors and windows so they're sealed properly from the exterior. Now that the basement doors arrived and Aaron has installed those, they also started the EIFS in the areaway. Since the EIFS installation is a process, they'll come back a couple of times to finish that section. There are some other minor details they need to take care of - such as completing the work around the step light electrical boxes and cleaning up the site. But we've been really pleased with Seasons Services' work on the EIFS installation. They're quick, professional, on the job when they say they're going to be there, and the quality of their work is very high. Here are some pictures of the Southern side:







Saturday, June 27, 2009

EIFS, Act 4

The final EIFS coat arrived by surprise. I went to the lot today to check on the sump pump, and Claudia's crew must have worked today, Saturday, to apply the final EIFS coat. Here is what it looks like:

EIFS, Act 3

This is what the next stage in the EIFS process looks like. The styrofoam is covered with a base coat that has a nylon mesh embedded in it. This already looks pretty close to the final product - the final coat (with color premixed into it) now goes on top of that.