I just received an email from our contractor, Aaron Holmes with Cornerstone Building, providing a revised time line to get the house under roof and interior framing completed. I thought I'd share it here:
- Complete stacking of TerraBricks above window and door headers & create Forms for the Bond Beam - this week
- Inspection of Bond Beam by City - Monday morning
- Pour Bond Beam - Monday afternoon or Tuesday morning
- 2 days for bond beam to cure before removing forms
- Framing for Roof & interior first floor - April 30th & May 1st
- WeatherShield Doors & Windows delivered and installed May 1st
- Electrical & Plumbing Rough-ins in first floor - Week of May 4th
As you may recall from the house plan post (see post entitled For Larry M.) there is no second story of the house, so the list above is a substantial amount of work to get the house closed up so interior projects can be initiated. Very exciting! Let's hope everything stays on track!