Thursday, September 3, 2009

Holey, Holey, Holey

Bob DeMarr's crew came back to core drill some holes through the foundation and the TerraBricks for the TRV fresh air inlet and exhaust and the fireplace fresh air inlet. In addition, Piedmont Roofing came back and completed the roof penetrations for the fireplace chimney and the kitchen exhaust hood pipe.

TRV Fresh Air Inlet:

TRV Exhaust:

Fireplace chimney:


For Range Hood:

For Dryer Vent:

Friday, August 28, 2009

Friday Progress

A few steps forward, a few steps nowhere. Bernie from Clarke County Plumbing connected both our sump pumps, and removed our temporary sump. Once power is connected to the house, we'll have two sumps running as necessary to ensure the water level stays tame (below the house, that is).

The sump outflow into the drain tile:

A step nowhere was the power connection. Dominion Power talked a good talk about service standards to connect the permanent power, promising an install within three weeks of the order date. We originally were told it would be last week. Then on Monday, we were promised this week, absolutely, the power would be connected. Miss Utility has spray painted all of our neighbors' yards so often that it looks like kids came through marking graffiti! But still no permanent power service. We'll stay on their case - we need the power to be connected on Monday, or we may have to manage new challenges.

That new challenge is the delivery of the rainwater recapture tanks. Three tanks, 1,400 gallons per tank, totaling 4,200 gallons of rainwater. Those, too, were supposed to have been delivered this week, but they didn't make it. We didn't push that at all since Dominion Power's subcontractor has been a no-show.

The folks at ARS continue to do a great job installing the ducting for the TRV. They'll be back on Tuesday and they expect to finish then. The weather hoods for the TRV were supposed to come in today, but...you guessed it...they didn't. We're hoping they'll arrive on Monday, and Bob DeMarr's crew can come out to drill the holes in the TerraBricks for the TRV air inlet and exhaust, as well as the dryer exhaust and fireplace fresh air inlet. Demarr has a core drill which will work perfectly for each cut. Tools are a wonderful thing!

Piedmont Roofing came today and installed the flashing around the East, South, and West side of the house. It looks like they did a nice job, but Aaron will have to inspect it when he's back on our project next week. We don't know if Piedmont re-sealed the flashing on the Northern side, which seems to have been allowing water through at the seams.



And we inspected Bartley's work with the concrete floor. Overall, the floor is really cool and it's definitely the contemporary look we're going for. Bartley's crew did a pretty good job with making the floor as smooth as possible. My three complaints are: 1) the shower was poured to the wrong height - it's too low as compared to where the drain was set, and now the water won't go down the drain unless we install tile on the shower floor which will cost us more money and is not the look we want. 2) they tracked mud into the still-wet concrete, so we have a few spots throughout the first floor where one can see mud in the now-dry concrete. The crew knew this was to be our final floor finishing - nothing on top except some soy-based stain. We explained that to them before they poured and insisted they be extremely cautious as to not track any dirt or debris in, or allow any dirt or debris to rise to the top, so it was irresponsible of them to allow this. The good news is the soy-based stain color is espresso brown, so it probably won't be a problem at all. I just can't understand why workers simply ignore such important details. 3) The workers were extremely sloppy and they did not clean up their messes. There are drink containers around the house. But most disturbingly, they dumped concrete all over the place and did not clean it up. I heard Aaron give them very clear instruction, and I heard their acknowledgement understanding the instructions, that they needed to be extremely careful about where any concrete is dumped on the lot. It needed to be dumped on OSB (leftover from the parging project) at the front of the lot. Again, instructions ignored and it's extremely disappointing that Bartley's crew did not clean up after themselves. This weekend, Andreas and I will be out there cleaning up after Bartley's mess once again, then driving the concrete to the dump and paying for it to be recycled by Fairfax County. Question for any sub-contractors reading this - why is it so hard for your colleagues to follow some simple instructions/requests?

You can't see clearly in the picture, but here's the shower poured to the wrong height:


Here's their mess:





And, the moment you've been waiting for, the concrete first floor:








Saturday, August 22, 2009

Long Progress Report




Before I head off to San Diego for a quick work trip (27 hours out of town, 12 of which will be at an airport/on an airliner), I wanted to give a brief progress report on construction.

While we remain frustrated that several subcontractors think it's perfectly OK to not show up when they say they'll be there, there are some bright spots:

Tim Griffin from ARS has been working with us to calculate the HVAC loads for the house and determine the ducting requirements. An energy efficient, air sealed house is a lot different to work with than conventional construction. And our passive solar design adds another twist. Tim has experience with green construction and the Earthcraft Virginia program. And our budget constraints offered another challenge. Tim designed a system and lined up a crew - they're scheduled to start the duct installation on Monday.

The last four days were absolutely exhausting. Andreas had three off-days in a row, so I took some vacation days from work and also spent Wednesday morning on the project. We worked our tails off on the house. I wish everyone we're paying to assist and manage this construction project were doing the same.

Wednesday morning, Aaron and I installed the fan and the fresh air intake system to the fireplace and set that in place.

Starting on Thursday, I spent a full 10 hours on my hands and knees vacuuming the first floor of the house with the shop vac so there would be no dust and debris to contaminate the concrete floor when it's poured next week. Despite multiple requests for workers to clean their shoes before entering, most folks just kept walking in, tracking more dirt for me to vacuum up. I don't mean to sound so negative. But, really, how difficult is it to clean off your shoes before walking into the house, especially after you've been specifically asked to, with the reason for the request explained to you?

While I was inside vacuuming, Andreas was completing numerous projects, including digging a trench to install the drain tile so the sump pump outflow will run under our intended garden area into the stream at the back of the lot. It looks great and is ready for Bernie to install the two cast iron sump pumps next week.

Elmer sent a crew on Thursday evening to install the nailer strips along the exterior walls (the TerraBrick walls). This was to fix mistakes Aaron had made when he cut and installed nailer strips some time ago, but they were of varying heights, so they all had to be removed and trashed. One of the considerations when building with a solid exterior is how to place electrical outlets along those walls. Ours will be centered in a baseboard. The size of the nailer strip in our house is extremely important, as the electrical boxes are screwed into that, and it also is the nailer strip for the baseboards. It needed to be a specific height so that the 1.5" of concrete would not come into the electrical boxes and so the electrical outlets would be a consistent height throughout the baseboards. It was good to get that corrected, since we're hoping that Bartley will be able to come on Wednesday to pour the concrete floor on the main level of the house.

After months and months attempting to get Washington Gas to install service at our house, their subcontractors came on Thursday early afternoon to do the street cut. First thing Friday they were back to trench on the lot and bring the gas line to the back of the house. It was only after I made a phone call to an executive at Washington Gas & Light Holdings that we saw any action. That's all water under the bridge now, but here's a special thanks to WGL Holdings' Marcellous Frye for getting the right people on the job for us.

Piedmont Roofing's crew was supposed to come on Thursday, but they ran over on another project, so they were to be on our project early Friday morning. Mid-afternoon Friday, they finally showed up. But they were not prepared to do what Aaron said he asked them to do. So they installed the roof boots on the plumbing and radon vent and promised to come back on Saturday. They didn't show up this morning. They had several hours of work time before the rain, so it's disappointing they were no-shows.

Tom (the electrician) came on Friday morning and finished everything he needed to for the electrical rough-in inspection. Andreas scheduled that for 9am on Monday.

Accurate Insulation was scheduled to come Friday morning to install the rain gutters. Only one person showed up. He looked at our house and said he couldn't do it himself, so he'd have to get help and come back on Saturday. He said he'd be at our lot by 8am. We showed up at 8:10 and he was there, with a co-worker, only to inform us that the job was COD. Aaron never sent us a contract and most vendors accept payment afterwards. So I drove home to get the checkbook and was back on-site an hour later only to learn that the crew didn't have screws long enough to attach the downspouts through the EIFS and into the concrete columns. So I drove to Brown's Hardware in Falls Church, but they didn't have any 5" stainless steel screws the Accurate folks requested. I then went to Home Depot. They didn't have any either, so I bought some 4" screws (the longest they had) and some 5" lag bolts. As it turned out, neither of those options worked, but the 4" TapCons I had in my truck (leftover from affixing the extruded foam board to the basement walls) fit the bill. All of that running around was a waste of time. After they left, Andreas and I attached some drain tile to direct the water away from the house. As soon as we were done, the rain started to fall. So I don't have any pictures of the gutter and downspouts yet.

After weeks and weeks and weeks, Quality Window and Door sent a service guy out to repair the sliding glass doors that were difficult to slide, install some weather stripping on a sliding glass door that didn't have some, and fix the loose-fitting locks on two of the swinging exterior doors. This was the third service guy to come out to work on the doors. Well, he got most of it done, but we'll need a fourth visit. He didn't have any weather stripping with him, so he couldn't do that. He fixed the two sliding glass doors. And he fixed one of the two locks. Maybe the fourth time will be the charm and someone can bring weather stripping and properly fix that remaining jiggly lock problem. How difficult is this...really?

Loudoun Stairs supposedly was going to come by on Friday to measure for the staircase to the basement and also bring some photos of what the staircase would look like. But they didn't show up. Can anyone recommend a good (but affordable) stair company for some basic stairs into the basement?

Andreas and I installed the pex tubing on the first floor this afternoon (Saturday). We didn't finish until after dark so, again, no photos. Clearly we were focused on getting the job done and not on documenting that for the blog. Sorry folks. We'll snaps some pics later.

While I'm on a flight to the West Coast tomorrow, Andreas plans to clean the basement floor so that can dry and allow us to test some sample coloring for the concrete floor stain when I'm back on the project Tuesday evening. There's a lot more on the schedule for next week, but I guess it will get done only if the subcontractors show up. These days, I'm not holding my breath for that! And please don't ask me about the clerestory windows.



Thursday, July 30, 2009

100th Blog Post






This marks our 100th post. And I'm happy to report there's been some more progress. In the past couple of days, our recycling dumpster was hauled away. We filled two dumpsters during the construction, which is less than 1/2 what typical construction sends to the landfill. And many of the items placed in our dumpster will be recycled instead of dumped.

Bob Demarr's crew spent about 7 hours fixing the problems with the rough grading caused by Bartley Corp's team. Bartley's job foreman admitted to Andreas that they really don't do grading work - they don't have the right equipment or labor. That showed with the mess they created. It took Andreas more than 30 hours to dig out tree protection fencing Bartley ran over with a machine and dumped dirt on top of. I spent another 10 hours uncovering the Holly Tree roots they graded over, even though the root protection zone is clearly marked on the grading plan. Alas, we're now on the right path with grading. Demarr's crew hauled away a few truck loads of dirt today, leaving the lot looking much better than it has the past six months!

Inside, Bernie from Clarke County Plumbing, continued work on the rough-in plumbing. He put the vent pipes through the roof (now Piedmont Roofing will come back to seal that all up) and worked on the basement bathroom. Ferguson delivered the tub, toilet wall carrier and shower faucet rough-in and Bernie will install that soon. He also drilled through the EIFS to prepare for the outdoor shower piping, the hose bibs, and the sump pump piping. Unfortunately, he drilled the sump pump holes too high - the sump pump pipes were supposed to come out beneath the deck - so we'll have to work with Bernie to get that resolved.

Also inside, Aaron laid the pex tubing for the bathroom radiant floor heating. I want the shower floor to be as toasty warm as the rest of the bathroom floor, so that had to be laid today so a first layer of concrete can go over the pex tubing in the shower tomorrow. Bernie can then protect the shower floor properly with the rubber membrane and when the concrete floor is poured, it will work out perfectly.

Elmer's crew started work today on the parging. They spent the day applying a metal lathe around the doors and windows. They'll finish that tomorrow then apply the thin layer of cement to the walls and round out the edges by the doors and windows. After that cures, I can apply the American Clay Earth Plaster over the cement parging.

Jay with Quality Window & Door hasn't provided the exact date yet for the corrected clerestory windows to be delivered - hopefully that will be in the early part of next week so the cedar siding can go on Thursday morning.

Saturday, May 16, 2009

Weekend Summary

I truly was hoping to have positive news on the "Window Worries" post by now, but despite multiple conversations, our house designer, John Spears, and the folks at Quality Window & Door still have not come to any resolution. As happens so often, each side made mistakes and no one's willing to take responsibility. Hopefully continued discussions next week will lead to a quick resolution. We'll be in the third week of discussions. Enough talking, time for action!

Piedmont Roofing finished the installation of the standing seam metal roof. It looks awesome! Well, except one piece of metal on the North side fascia at the very back of the house, which looks severely dented. I was told by the roofers that it will be fixed when the drip edge is completed after the EIFS is installed. Piedmont Roofing's been a great company to work with - honest, helpful, responsive, quick. But I think we need to hold some money back from the final payment until it's resolved to our satisfaction.

Speaking of EIFS, we're chomping at the bit to get the extruded foam board and stucco installed. But that can't happen until our contractor, Aaron, caulks around all of the doors and windows as required by the EarthCraft House program. There are a host of other items that need attention over the next week in order for us to stay on track with Tier 3 certification, which is the EarthCraft Premium level.

We had an extremely informative meeting with Chris Conway (the Green Gobbler) with Conway Construction. Chris is our technical advisor for the EarthCraft program and he is worth his weight in gold! We don't need a psychologist while building a house, since we have Chris! Andreas and I went to DC on Friday morning and toured my friend Mike's townhouse which is in the final stages of a complete renovation. His house is absolutely beautiful and I can't wait to see the finished project. From there, we went to our construction project and met up with Chris. On the way out to our project, Mike asked what the value was in pursuing a green certification for the house. Most folks think we're getting tax credits or something similar. My answer to Mike was that EarthCraft is giving us peace of mind, since it's another set of eyes looking at this project and comparing the on-going work to an established, vetted standard. EarthCraft is our construction conscience ensuring the right thing's being done at all times. That's not to say that mistakes won't be made, but someone else is looking out for us to ensure they're not covered up in a way that would be harmful to us or to the environment. 

I'll interview our EarthCraft technical advisor, Chris Conway, and write that up for the blog in the coming weeks.



 

Tuesday, May 12, 2009

Roof, Roof! (And an update, or lack thereof, on the Window Worries)

Roof, Roof!

I'm pleased to report some positive news! After work this evening, I stopped by the house to see what progress was made on the installation of the standing seam metal roof that's being installed by Piedmont Roofing. The crew made a lot of progress today. Most of the metal roof has been installed. The metal is produced by Englert, which is located in New Jersey. They have an entire line of colors that have achieved EnergyStar ratings. The color we selected, matte black, is an exact match for the obsidian windows & doors from WeatherShield. I think the roof is looking great and it will be very attractive for many years to come. 

Last Friday afternoon, Tim Reed, the owner of Piedmont Roofing gave me a tour around the Middleburg, VA horse country where his company has done numerous standing seam metal roof installations. On the drive we were chatting about various roofing options. Englert's product has a 35 year color warranty and the roof will last even longer than that. If we had chosen an environmentally-unfriendly option, like asphalt shingles, the roof would last 10-15 years and cost 50-60% of the price. So we will have a much more attractive roof that will last many years longer, and is only a few thousand dollars more money. Take a look:





Window Worries Update:

I sincerely believed that we would have had a resolution to the window problem by now. It's been more than a week since the window issues had been identified. As you'll recall from the last post, Window Worries, I noted that there were problems with the clerestory windows (wrong size) and problems with the sliders on the Southern side (wrong glass).  I've spoken with our architect, John Spears, each day and he continues to follow up with Quality Window & Door. We still don't have a definite resolution, although John's been told that Quality Window & Door is working on a resolution. 

We greatly appreciate the comments that were submitted by you all, as well as the personal emails and phone calls on this subject. I remain optimistic that this will be resolved to our satisfaction. No one said construction won't come without its headaches, but this is a big one and we need it to be resolved very quickly.


Saturday, May 2, 2009

Shielded from the Weather

It's amazing what can happen in one day! Several key projects were completed (or mostly completed) yesterday. 

The crew from Piedmont Roofing installed the felt underlayment for the standing seam metal roof. So if the rain comes, as forecast, the house should stay nice and dry!

Quality Window & Door delivered all of our....you guessed it....our WeatherShield windows and doors. And there are a lot of them!  All of the windows, with the exception of the basement windows, have been installed. The basement windows will be installed on Monday morning. We still need to buy a double door for the basement area way entrance. We looked last weekend at Community Forklift, but they didn't have any double doors in their inventory. I'll try to get to Habitat for Humanity's ReStore in Alexandria this weekend to see if I have better luck there.

The framing crew also built out most of the interior walls as well. I am a little concerned about some of the door/entrances that are supposed to be framed for pocket doors, since I don't see how a pocket door could possibly work the way they framed it. And the closet along the North wall of the master bedroom is so narrow, I don't think a suit could hang in there. So that's not good at all. I'll be heading out to the house this morning with a suit (on a hanger) to try to closet on for size, so to speak.  I couldn't possibly live with a closet like that as it would be a daily reminder of one of the worst hotel stays I've had recently - the Radisson Hotel in the Stapleton section of Denver -- which had a closet built the same way. All my clothes had to be pushed back on an angle in order to close the closet door, resulting in wrinkles. (I'm not that tightly wound -- the closet wasn't what made the hotel so terrible, there were a host of other negative things, but I've digressed from the point of this post, so I'll stop my hotel complaining now.) Our contractor, Aaron, will be on-site Monday morning with the framing crew to ensure any mistakes or problems are promptly corrected.

Finally, the folks who will be doing the EIFS on the exterior of the house supposedly dropped of a sample of a smoother, lighter grey finishing since the one they did for the Renovation Nation filming is a bit more course and dark than we'd like. I couldn't find the sample and didn't want to get in the way of the framers, so I didn't poke around too much looking for it. I'll see it today.









Thursday, April 30, 2009

Run for Cover!!

And that cover could be under the roof of our house! Yes, there's a roof! Amazing!

Wow, what a relief to have a fast, professional crew back on the job! Hector and his framing crew were back on-site today and they have the entire roof decking up! The forecast for rain throughout the day didn't come true - instead we had grey skies, which were perfect for working outside. The crew will continue work early in the morning on some of the clerestory window framing on the South side and then start interior wall framing. 
The doors and windows are scheduled to be delivered and installed tomorrow, so the house will be completely different looking then!

Before work this morning, I talked today with the folks at Piedmont Roofing who have been very helpful as we've worked through the standing seam metal roof color options and different styles for the related metal items, such as the drainspouts. They'll be on-site this Friday as well, to install the tar/felt underlayment on the roof deck.

And it was great to get back in touch with Abdess from the Ferguson Showroom near Dulles Airport. We spent many hours with Abdess last August picking out plumbing fixtures. He will order those for us and we will have them ready for the plumber to install next week when he's on-site to do the rough-in plumbing in the main level.