Monday, June 22, 2009
Thanks, Jeff!

Saturday, June 20, 2009
Wrong Windows Removed, More Flooding
Puddles, Puddles everywhere
This rain is driving me nuts! Bartley returned on Tuesday with the repaired machine to continue the grading work. The clay dirt was too wet for them to complete the job, so they'll have to come back again after 4-5 days of no rain, which will give the dirt time to dry out. At this rate, I don't think we'll ever have that kind of dry spell!
While doing the grading, the guy from Bartley drove right into the corner of our house, completely destroying three of the extruded foam board panels. Hopefully when the EIFS installers come, they will be able to easily add new foam board there and make it like new. You can see the foam board we cut away in the fourth picture below.
On Thursday, when I was in an important all-day meeting, I received an email from my neighbor to the South stating that our silt fence needed attention. You will see in the final picture where the torrential rain storms that afternoon, following days of steady rain, were just too much for any silt fence to handle. I went that night and put up an extra layer of new silt fencing, hoping that holds in the future. Once the grading is complete, hopefully this won't occur again. If it does, we might be forced to incur even more water mitigation expenses (which we cannot afford) in terms of draintile to prevent water run-off.
Prepping for EIFS Installation
In order to secure the best possible price for the EIFS installation (that's the extruded foam board and synthetic stucco system on the exterior of the house), we agreed to attach the basement extruded foam board to the house using TapCon concrete screws. That saved time for the installers, which saved us money. Andreas did the work, which took a few hours, about 100 TapCon screws with large washers, and five concrete drill bits to pre-drill the screw hole. Doesn't it look great? Now the EIFS installers will be able to nicely match their foam board with ours for a professional installation.
Wednesday, June 10, 2009
Grading in Progress



Thursday, June 4, 2009
Rain, Rain, Go Away
We're receiving quotes for ceiling and wall insulation (the wood-framed clerestory wall, not the Terrabrick wall). Closed cell spray foam is the best choice, but it's the most expensive by far. So we're considering a hybrid which will be a closed cell spray foam application that would be about 2-3" thick and then a zero formaldehyde blown in fiber (it's called the spider system, since a web holds it all in). Combined, we will have an R50 insulation value for the ceiling and R23 for the clerestory walls. That option is several thousand dollars less expensive than 100% closed cell spray foam, which would give us about an R41 insulation value. We're still receiving quotes, so if anyone has a good company that's experienced in spray-foam insulation, please let us know.
Importantly, all of the quotes we received also include a foam sealant or high-grade caulking to seal all penetrations in the thermal envelope. This will be a very tight house!
Tuesday, June 2, 2009
Welcome Back Aaron
Shopping Spree
Tuesday, May 26, 2009
Recycling Dumpster, Window Update, Pranksters, and Thieves

About a month ago, I asked for suggestions from readers of this blog on where we might find a recycling dumpster for our construction materials. Sat Jiwan responded with some recommendations, Andreas made some phone calls, and we ended up choosing Environmental Alternatives, Inc. in Clarksburg, MD, which was one of the companies Sat Jiwan had recommended to us. Believe it or not, their pricing was less expensive than traditional dumpsters that just drop off at the landfill, and they'll also provide us with a detailed report of what we placed in the dumpster for recycling. That report is important for the EarthCraft House Virginia premium certification we're pursuing.
Sunday, May 17, 2009
Community Outreach
Saturday, May 16, 2009
Weekend Summary
Tuesday, May 12, 2009
Roof, Roof! (And an update, or lack thereof, on the Window Worries)




Sunday, May 10, 2009
Window Worries


Saturday, May 2, 2009
Shielded from the Weather




Thursday, April 30, 2009
Run for Cover!!
Wow, what a relief to have a fast, professional crew back on the job! Hector and his framing crew were back on-site today and they have the entire roof decking up! The forecast for rain throughout the day didn't come true - instead we had grey skies, which were perfect for working outside. The crew will continue work early in the morning on some of the clerestory window framing on the South side and then start interior wall framing.
The doors and windows are scheduled to be delivered and installed tomorrow, so the house will be completely different looking then!
Before work this morning, I talked today with the folks at Piedmont Roofing who have been very helpful as we've worked through the standing seam metal roof color options and different styles for the related metal items, such as the drainspouts. They'll be on-site this Friday as well, to install the tar/felt underlayment on the roof deck.
And it was great to get back in touch with Abdess from the Ferguson Showroom near Dulles Airport. We spent many hours with Abdess last August picking out plumbing fixtures. He will order those for us and we will have them ready for the plumber to install next week when he's on-site to do the rough-in plumbing in the main level.
Wednesday, April 29, 2009
Shaken, Not Stirred

Monday, April 27, 2009
Falls Church City Green Home Award Program
Rather than re-inventing the green wheel, the City staff smartly decided it would be more effective and efficient to point to other rigorous programs and recognizes those as qualifying for the City's program. Homeowners and developers who choose to participate in the Falls Church City Green Home Award Program will be awarded for doing something positive to improve the sustainability of the environment and the community. We were the first house to submit an application for this program and we hope our construction pace picks up so we're the first house to be awarded under the program!
The City hasn't yet announced what the award will be. We'd love it if it were exemption from real estate taxes, but that's highly unlikely! From our perspective, we're not doing this for any recognition or award; green construction simply is the right thing to do.
Here's a picture of the City's sign in our front yard.
Friday, April 24, 2009
Interesting, Quick Read Article on Planet Green's Website
Thursday, April 23, 2009
Dumpster - Recycle
We were trying to avoid getting a dumpster, since we don't want to add to local landfills. However, it seems that this may be inevitable, particularly since we promised the owner of the house next door that we'd clean up her back yard since she allowed us to use it to store the dirt from the basement excavation while we made the TerraBricks. (Thank you again!) The two weeks we anticipated using her back yard is now over two months, so we want to ensure we do a fantastic job cleaning up the lot which includes a whole host of items (junk furniture, a plug-in heater, old paneling) that are sitting behind her house, as well as the dead tree limbs, brush, etc. that's located at the back of the yard.
Here's my question for you: do you know of any company that will drop a dumpster for a few weeks, then haul it away and go through the materials to recycle as much as they can? Or, do you have other thoughts on how we can handle this in an environmentally-friendly manner? Any and all leads are welcome. Obviously we are very price sensitive as this is an item we have not budgeted for.
Please comment below. Thanks!
Timeline Until We're Under Roof
- Complete stacking of TerraBricks above window and door headers & create Forms for the Bond Beam - this week
- Inspection of Bond Beam by City - Monday morning
- Pour Bond Beam - Monday afternoon or Tuesday morning
- 2 days for bond beam to cure before removing forms
- Framing for Roof & interior first floor - April 30th & May 1st
- WeatherShield Doors & Windows delivered and installed May 1st
- Electrical & Plumbing Rough-ins in first floor - Week of May 4th
As you may recall from the house plan post (see post entitled For Larry M.) there is no second story of the house, so the list above is a substantial amount of work to get the house closed up so interior projects can be initiated. Very exciting! Let's hope everything stays on track!